Project Schedule, Detour Plan and Final Configuration depicted at bottom of page.

Friday, May 30, 2014


This week A. Lamp Concrete Contractors’ tree removal subcontractor was onsite removing trees until Thursday.  The tree removal subcontractor will be back later in the project to remove the remainder of the trees that are not currently in conflict with the proposed work.

Next week A. Lamp Concrete Contractors will be onsite performing various operations in preparation for storm sewer work.  This will include installation of erosion control measures, existing fence removal, curb and sidewalk removal needed for temporary pavement installation, and temporary pavement installation along the south side of West Lake Ave. from Greenwood Rd. to the east of Pickwick Ln., and on the north side of West Lake Ave. from Elmdale to the west approximately 300 feet.

The week of June 9 it is anticipated that storm sewer work will begin west of the railroad tracks with A. Lamp installing pipe on the south side of the road.  For this work to take place the detour may be going into effect late next week or early in the week of June 9.  Please note, when the detour goes into effect West Lake Avenue and Greenwood Road will be closed to thru traffic.  Local traffic will be able to access their residences or businesses, but please expect delays