Project Schedule, Detour Plan and Final Configuration depicted at bottom of page.

Friday, June 27, 2014


This week A. Lamp Concrete Contractors' roadway crew shifted traffic and began to utilize the temporary pavement on the south side of West  Lake Avenue between Greenwood Road and North Lake Terrace.  A. Lamp then began pavement removal in the existing westbound lane of West Lake Avenue from Greenwood Road to approximately 200 feet west of North Lake Terrace. 

A. Lamp also had their storm sewer crew onsite again this week completing storm sewer installation on West Lake Avenue west of the railroad tracks. After completing the storm sewer west of the railroad tracks the crew relocated to the east end of the project and began storm sewer installation on West Lake Avenue between North Lake Terrace and Pickwick Lane.

Next week, A. Lamp is scheduled to continue storm sewer installation from Pickwick Lane to the west.
 
As a reminder, West Lake Avenue is closed to thru traffic.  Local access will always have access to businesses and residences within the project limits, but please expect delays.  All regional traffic should use the posted detour.  Thank you for your patience during the construction.