Project Schedule, Detour Plan and Final Configuration depicted at bottom of page.

Friday, July 11, 2014


This week A. Lamp Concrete Contractors continued storm sewer installation on West Lake Avenue from Pickwick Lane west to Greenwood Road.

Next week, A. Lamp is scheduled to continue storm sewer on West Lake Avenue from Greenwood Road to the west. Longer traffic delays are expected when work occurs in the intersection.

During work this week traffic was restricted to 1 lane during working hours, which will be a common procedure for this project.  The detour was put into effect to re-route regional traffic (traffic that is just passing through this area) away from the construction site.  For the remainder of the project, the site will be closed to thru traffic and local traffic (traffic that has destination points within the project area) should expect delays."