Project Schedule, Detour Plan and Final Configuration depicted at bottom of page.

Monday, August 11, 2014

Last week A. Lamp Concrete Contractors continued storm sewer lateral installation on West Lake Avenue in various locations.  A. Lamp also began survey work associated with the roadway excavation.  The electrical subcontractor was also onsite last week to discuss traffic signal work to begin soon.

This week, A. Lamp is scheduled to begin excavation of the roadway starting at the east end of the project.  This will include removal of the remain asphalt roadway.  Heavy traffic delays should be expected during this work.  Minor underground utility work will take place this week.

Please be reminded that the detour was put into effect to re-route regional traffic away from the construction site.  Any traffic that is not going to or from a business or residence within the project limits should use the detour to avoid lengthy delays.