Project Schedule, Detour Plan and Final Configuration depicted at bottom of page.

Sunday, August 3, 2014

This week A. Lamp Concrete Contractors completed storm sewer main line installation on West Lake Avenue from Greenwood Road west to the railroad tracks.  After completion of storm sewer main line, A. Lamp began storm sewer lateral installation from Pickwick Lane to Greenwood Rd.

Next week, A. Lamp is scheduled to continue storm sewer laterals on West Lake Avenue from Greenwood Rd. towards the railroad tracks, which will include work in multiple locations per day.  Additionally, A. Lamp's electrical subcontractor is scheduled to begin work associated with traffic signals.

During work this week traffic was restricted to 1 lane during working hours, which will be a common procedure for this project.  The detour was put into effect to re-route regional traffic away from the construction site.  For the remainder of the project, the site will be closed to thru traffic and local traffic should expect delays.