Project Schedule, Detour Plan and Final Configuration depicted at bottom of page.

Friday, August 29, 2014


This week A. Lamp Concrete Contractors was removing existing concrete base course pavement, existing sidewalk and existing concrete curb on the north side of West Lake Avenue.  A. Lamp also began excavation of the roadway on the north side of West Lake Avenue from the east end of the project.

Next week A. Lamp is scheduled to continue excavation of the roadway on the north side of West Lake Avenue from 3120 West Lake Avenue to 3340 West Lake Avenue.  Additionally, on Friday September 5, 2014  A. Lamp is scheduled to install curb and gutter on the north side of West Lake Avenue.