Project Schedule, Detour Plan and Final Configuration depicted at bottom of page.

Friday, September 5, 2014

This week A. Lamp Concrete Contractors completed earth excavation on the north side of West Lake Avenue in preparation for roadway construction.  Additionally, this week A. Lamp began installation of the concrete curb and gutter along the north side of West Lake Avenue from approximately 150’ west of North Lake Terrace to Pickwick Lane.  A. Lamp’s electrical subcontractor was also onsite this week installing electrical conduit for the traffic signals.

 

Next week, A. Lamp Concrete Contractors is scheduled to complete the majority of the concrete curb and gutter on the north side of West Lake Avenue, begin prepping for asphalt paving, and continue working on miscellaneous concrete work around the project.  Mid-week A. Lamp’s asphalt contractor is scheduled to pave two of the three layers of asphalt on the north side of West Lake Avenue. “