Project Schedule, Detour Plan and Final Configuration depicted at bottom of page.

Monday, October 6, 2014


Last week A. Lamp Concrete Contractors completed excavation and installed stone in the locations of pavement widening on Greenwood Road.  A. Lamp was also excavating for sidewalk and pouring sidewalk in various locations on West Lake Avenue.  Additionally, A. Lamp’s electrical subcontractor was onsite installing foundations and hand holes for traffic signals.

This A. Lamp is scheduled to continuing pouring sidewalk and bike path on West Lake Avenue for most of the week.  A. Lamp’s asphalt paving subcontractor is scheduled to be onsite installing asphalt pavement widening on both sides of Greenwood Road.  The electrical subcontractor is also scheduled to be onsite next week completing various electrical items associated with the traffic signal installation.