Friday, October 24, 2014

This week A. Lamp Concrete Contractors was pouring concrete for the bike path on the south side of West Lake Avenue in various locations between Pfingsten Road and West Lake Avenue.  Additionally, A. Lamp was installing much of the remaining storm sewer and grading in various locations.  On Thursday the asphalt subcontractor installed prime on the street in preparation for paving, which is scheduled to take place on Saturday.

Next week, A. Lamp Concrete Contractors is scheduled to continue and possibly complete concrete sidewalk and driveways.  The electrical subcontractor is scheduled to begin installation of the traffic signal posts and wiring.  Additionally, the pavement marking subcontractor is scheduled to install the final pavement markings on the new surface course asphalt.