Project Schedule, Detour Plan and Final Configuration depicted at bottom of page.

Friday, September 26, 2014

Concrete Work Continues

Last week A. Lamp continued to excavate, install aggregate base, and pour concrete for the bike path, sidewalks, curb & gutter, and driveways in various locations on the project.  A. Lamp also completed the underground utility improvements including structure adjustments, fire hydrant adjustment, and miscellaneous storm sewer work.  The asphalt paving subcontractor, Peter Baker & Sons, was onsite this week installing asphalt pavement at the intersection of West Lake and Greenwood Road as well as at the intersection of Pickwick Lane south and West Lake Avenue.

Next week A. Lamp Contractors will continue to excavate, install aggregate base course, and pour concrete for the bike path, sidewalks, curb & gutters, and driveways. The contractor will also begin excavating and preparing the roadway for the widening of Greenwood Road south of West Lake Avenue and for the extension of Greenwood Road north of West Lake Avenue. The electrical contractor, Elmund Nelson, will be on-site installing the concrete pole foundations and wiring conduit in preparation for the new traffic signals at the intersection. The tree removal subcontractor will be on-site removing the remaining trees scheduled to be removed in conflict with the improvements.

Monday, September 22, 2014


Last week A. Lamp Concrete Contractors was installing concrete bikepath, sidewalk, curb & gutter, and driveway pavement in various locations on West Lake Avenue from Pfingsten Road to North Lake Terrace.  In addition, A. Lamp was removing pavement, excavating, and installing the new stone road base.

This week A. Lamp will continue to pour concrete bikepath, sidewalk, curb & gutter, and driveway pavement in various locations on the project.  A. Lamp will also have an underground crew onsite completing the remaining underground utilities including structure adjustments, fire hydrant adjustment and miscellaneous storm sewer work.  Additionally, A. Lamp’s asphalt subcontractor will be onsite this week installing asphalt pavement on Greenwood Road (including the intersection of West Lake) and on Pickwick Lane south of West Lake Avenue
.

Friday, September 12, 2014


This week A. Lamp Concrete Contractors completed the installation of curb and gutter associated with the roadway on the north side of West Lake Avenue.  A. Lamp also completed prepping of the stone base course in preparation for paving.  On Friday and Saturday, A. Lamp’s asphalt subcontractor was installing the asphalt binder course on the north side of West Lake Avenue. 

Next week A. Lamp is scheduled to continue miscellaneous concrete work on the project.  This will include concrete driveway curbs, sidewalks, and roadway curb and gutter that was previously gapped.
 
Due to conflicts with some existing utilities, work in certain locations may be delayed until the utility companies relocated their facilities.

Friday, September 5, 2014

This week A. Lamp Concrete Contractors completed earth excavation on the north side of West Lake Avenue in preparation for roadway construction.  Additionally, this week A. Lamp began installation of the concrete curb and gutter along the north side of West Lake Avenue from approximately 150’ west of North Lake Terrace to Pickwick Lane.  A. Lamp’s electrical subcontractor was also onsite this week installing electrical conduit for the traffic signals.

 

Next week, A. Lamp Concrete Contractors is scheduled to complete the majority of the concrete curb and gutter on the north side of West Lake Avenue, begin prepping for asphalt paving, and continue working on miscellaneous concrete work around the project.  Mid-week A. Lamp’s asphalt contractor is scheduled to pave two of the three layers of asphalt on the north side of West Lake Avenue. “